The brutal $346M math behind Galaxy’s high-stakes race to build CoreWeave’s Texas AI mega-center

CoreWeave’s $20 billion funding haul shows why Bitcoin is losing the competition for liquidity

Galaxy Digital’s $3.507 billion financing for its CoreWeave data-center build in Texas comes with a steep worth: about $346.3 million in annual curiosity.

A Galaxy venture subsidiary priced the 9.875% senior secured notes on July 23. The deal is slated to shut July 28, and the notes mature on Aug. 1, 2031.

The financing is meant to cowl a part of two buildings with eight knowledge halls on the Helios campus. The amenities are deliberate for 400 megawatts of utility capability and 260 MW of important IT capability, with some proceeds additionally funding debt-service reserves.

CoreWeave’s $20 billion funding haul shows why Bitcoin is losing the competition for liquidity
Related Reading

CoreWeave’s $20 billion funding haul shows why Bitcoin is losing the competition for liquidity

CoreWeave’s financing haul shows how AI is pulling capital and liquidity away from Bitcoin.
Jul 11, 2026
·
Oluwapelumi Adejumo

The 9.875% coupon works out to $346.3 million in annual curiosity, paid in money each Feb. 1 and Aug. 1 beginning in 2027. The first cost covers solely a part of a yr, however Galaxy has not disclosed the precise quantity.

Repayment begins when building ends

Principal reimbursement runs on a distinct schedule. The notes are due to amortize at 4% of authentic principal every year, topic to adjustment. That equals $140.28 million yearly earlier than changes, paid in semiannual installments, with the primary cost date no less than 10 months after venture completion.

Hut 8 AI landlord data center strategy turns Bitcoin collateral into bridge capital
Related Reading

Hut 8 AI landlord data center strategy turns Bitcoin collateral into bridge capital

Hut 8’s $16.8 billion AI data center lease base shows how power access, project debt, and Bitcoin collateral are financing a move beyond mining.
May 27, 2026
·
Liam ‘Akiba’ Wright

Interest begins on a hard and fast schedule, whereas principal repayments wait till building is full and will be adjusted. Creditors will maintain first-priority claims on practically all venture property and the dad or mum firm’s stake within the issuer.

The disclosed liens cowl Galaxy Helios Data Centers II LLC, its venture guarantor and the parent-held fairness within the issuer. They don’t prolong to Galaxy Digital’s property typically.

CoreWeave committed to approximately 260 MW of incremental critical IT load for Phase II in April 2025. Galaxy described the phrases as considerably comparable to its beforehand introduced 15-year, 133 MW Phase I settlement.

Delivery is now the central working take a look at. On July 6, Galaxy stated Phase I had been accomplished on schedule and that Phase II data-hall deliveries were expected to begin in the first half of 2027.

Bitcoin miner CleanSpark signed a $6.6B AI lease before securing the $2.1B required to build it
Related Reading

Bitcoin miner CleanSpark signed a $6.6B AI lease before securing the $2.1B required to build it

The 175 MW contract creates a long revenue path while funding terms remain undisclosed and missed milestones may reduce rent or end the lease.
Jul 15, 2026
·
Liam ‘Akiba’ Wright

The building schedule now carries a transparent monetary worth. Interest begins in 2027, however principal repayments wait till the venture is completed, placing Galaxy’s supply timeline on the coronary heart of its CoreWeave deal and debt obligations by means of 2031.

The put up The brutal $346M math behind Galaxy’s high-stakes race to build CoreWeave’s Texas AI mega-center appeared first on CryptoSlate.