Bitcoin miners have amassed $100 billion of AI deals, but almost none of the revenue exists yet
Bitcoin miners have signed greater than $100 billion in AI contracts whereas producing barely $1.1 billion in annualized revenue.
More than 4 gigawatts of synthetic intelligence and high-performance computing capability are below contract throughout publicly traded miners tracked by CoinShares, but solely about 550 megawatts are presently billing.
Still, traders are assigning a steep premium to corporations making the AI transition. Miners with contracted AI or HPC capability commerce at a median of 12.9 occasions enterprise worth to next-12-month gross sales, in contrast with 3.7 occasions for miners with out such agreements.
However, this premium is more and more tied to an asset miners collected for Bitcoin but AI builders now badly want: grid-connected energy.
Scarce energy turns mining websites into premium AI property
The worth of current mining campuses is rising as new data-center tasks run into longer allowing processes and more and more congested energy grids throughout the US.
CoinShares recorded not less than 225 moratoriums or restrictions on data-center growth throughout 30 states, with 151 nonetheless in pressure, in its newest trade report. New York has launched a statewide pause on environmental permits for amenities of 50 megawatts or extra, whereas restrictions have unfold at state and county ranges elsewhere.
Those constraints are colliding with a US grid interconnection queue of roughly 2,600 gigawatts. Projects accomplished in 2025 waited a median of greater than 5 years between getting into the queue and changing into operational, giving miners with energized land and current grid connections a bonus over builders ranging from scratch.
The potential revaluation is substantial.
A current transaction cited by CoinShares valued three absolutely leased Northern Virginia AI knowledge facilities at roughly $27 million per megawatt. Some publicly traded miners with energized but unleased capability are valued under $3 million per megawatt.
That hole exists regardless of the high value of turning a BTC mining website into an AI facility. CoinShares estimates retrofits can require about $8 million to $15 million per megawatt, in contrast with roughly $700,000 to $1 million per megawatt for Bitcoin mining infrastructure.
However, the economics can nonetheless justify the expense. AI infrastructure presently generates an estimated $1.5 million in annualized revenue per megawatt for miners, roughly 3 times the $500,000 accessible from Bitcoin mining below present circumstances.
Investors have responded earlier than most of that revenue has arrived. Ten of the 12 mining corporations adopted by CoinShares gained between 70% and 195% throughout the second quarter. Keel Infrastructure, previously Bitfarms, surged 194.4% even because it shut down its Bitcoin mining operations.
Miners at the moment are paying to depart Bitcoin
The monetary incentive has turn out to be sturdy sufficient that some operators are absorbing losses and abandoning gear to speed up the transition.
Core Scientific paid $41.9 million throughout the second quarter to terminate an settlement overlaying about 15 exahashes per second of next-generation Bitcoin mining gear because it redirects infrastructure towards AI and HPC customers.
Its remaining self-mining enterprise posted a -56% gross margin during the period. Some machines proceed working partly to offset energy obligations whereas websites are transformed to different makes use of.
Keel has gone additional. The firm shut down its remaining Bitcoin mining operations on June 29 and is anticipated to report no mining revenue in the third quarter, making its nearly 200% share-price rally throughout the second quarter one of the clearest examples of traders rewarding the transition.
IREN plans to considerably full its transfer away from mining by Dec. 31 after recording lots of of thousands and thousands of {dollars} in impairments and markdowns on mining gear.
Its revenue combine has already flipped. AI cloud revenue reached $70.5 million in its newest quarter, surpassing the $66.7 million generated from Bitcoin mining for the first time.
Cipher Digital has stopped planning new mining capital expenditure and expects Bitcoin manufacturing to turn out to be immaterial forward of a possible exit by the finish of 2027. TeraWulf has additionally retired mining buildings as HPC leases take a bigger share of its enterprise, with these contracts accounting for 71% of quarterly revenue.
CoinShares estimates that not less than 35 EH/s is scheduled to depart publicly listed miners as these conversions proceed, equal to roughly 4.7% of the Bitcoin network’s recent 750 EH/s hashrate.
IREN accounts for 23.2 EH/s of put in capability, whereas Cipher’s Odessa operation contributes one other 11.6 EH/s. TeraWulf is individually winding down roughly 145 MW of remaining mining capability.
Meanwhile, the shift may very well be tougher to reverse at the same time as Bitcoin’s restoration improves mining economics.
Bitcoin’s rebound to about $77,000 has lifted hash value to roughly $38 per petahash per second per day, pushing most listed operators again above money breakeven after a troublesome second quarter. The weighted common ex-tax money value of producing one Bitcoin reached about $75,500 throughout the interval, when the token ended June close to $58,400.
A stronger Bitcoin rally may nonetheless change capital-allocation selections for corporations that have saved their mining choices open. CoinShares expects new mining funding to pay attention amongst operators together with Riot Platforms, MARA Holdings, HIVE Digital and Bitdeer, which retain better flexibility to broaden their fleets if returns enhance.
That optionality is shrinking for miners as the AI transition deepens. Several have dedicated websites to leases lasting so long as 15 years, whereas Core Scientific’s choice to spend almost $42 million canceling mining {hardware} illustrates how a lot capital has already been redirected.
$100 billion backlog now faces a buildout take a look at
The similar expectations lifting miner valuations at the moment are pressuring operators to show signed contracts into functioning knowledge facilities.
Only about 550 MW of greater than 4 GW of contracted capability is presently billing, leaving most of the sector’s $100 billion-plus backlog depending on future building, financing and deployment.
The scale of that hole means traders are valuing a lot of the sector on infrastructure that has yet to provide revenue.
Some of the conversion is underway. Core Scientific is billing 437 MW, Cipher started amassing hire from its Black Pearl facility in August, and IREN is focusing on $4 billion in annual working recurring revenue by December.
CoinShares expects the trade’s AI and HPC revenue run charge to greater than double by its subsequent report.
That progress would start narrowing the gulf between the contracts already signed and the roughly $1.1 billion of revenue presently being generated. It would additionally strengthen the case for miners whose energy portfolios are being valued extra like future data-center platforms than Bitcoin operations.
The threat is that building, financing, or energy infrastructure fails to reach rapidly sufficient.
Billions of {dollars} nonetheless must be deployed to transform contracted megawatts into revenue-producing amenities. Companies that full these tasks on schedule will start placing money circulation behind the valuations traders have already assigned.
Those that don’t may stay priced for an AI enterprise that exists principally in backlog.